I’m starting a new position in two weeks. How do you determine the capacity of a new team to start off a sprint?
Lost your password? Please enter your email address. You will receive a link and will create a new password via email.
Please briefly explain why you feel this question should be reported.
Please briefly explain why you feel this answer should be reported.
Please briefly explain why you feel this user should be reported.
You guess. And you’ll be wrong. And that’s okay.
Capacity is just a mechanism to help the team determine a Sprint Goal they can deliver; they’ll then inspect and adapt daily to meet that goal. But it’s okay to make a prediction (ie a Goal), get it wrong, then inspect and adapt.
I’d suggest it’s more important to slice the work down into stuff that 1-2 people can do in 1-2 days, and make sure the team understands the work. A bunch of other stuff won’t go well in the first Sprint too.
So – you’ll have a lot to unpack in the retrospective…