Sign Up

Captcha Click on image to update the captcha.

Have an account? Sign In Now

Sign In

Captcha Click on image to update the captcha.

Forgot Password?

Don't have account, Sign Up Here

Forgot Password

Lost your password? Please enter your email address. You will receive a link and will create a new password via email.

Captcha Click on image to update the captcha.

Have an account? Sign In Now

Sorry, you do not have permission to ask a question, You must login to ask a question.

Captcha Click on image to update the captcha.

Forgot Password?

Need An Account, Sign Up Here

Sorry, you do not have permission to add post.

Captcha Click on image to update the captcha.

Forgot Password?

Need An Account, Sign Up Here

Please briefly explain why you feel this question should be reported.

Please briefly explain why you feel this answer should be reported.

Please briefly explain why you feel this user should be reported.

Sign InSign Up

Ask Agile

Ask Agile Logo Ask Agile Logo

Ask Agile Navigation

  • Home
  • Blog
  • Contact Us
Search
Ask A Question

Mobile menu

Close
Ask a Question
  • Community Help
    • Kanban
    • Scrum
    • Scaled Scrum
    • Liberating Structures
    • Culture
    • Small Talk
    • Team Dynamics
    • Job Opportunities
    • Self-Promotions, Selling Services, Tool Promotions
  • Home
  • Blog
  • Contact Us

Ask Agile Latest Questions

Anonymous
  • -1
Anonymous
Asked: July 25, 20222022-07-25T10:24:34-05:00 2022-07-25T10:24:34-05:00In: Scrum

How do you determine the capacity of a new team to start off a sprint?

  • -1

Hello guys,

I’m starting a new position in two weeks. How do you determine the capacity of a new team to start off a sprint?

capacitynewsprintteam
  • 1 1 Answer
  • 73 Views
  • 0 Followers
  • 0
Share
  • Facebook

    You must login to add an answer.

    Captcha Click on image to update the captcha.

    Forgot Password?

    Need An Account, Sign Up Here

    1 Answer

    • Voted
    • Oldest
    • Recent
    1. GuyM
      GuyM
      2022-07-26T04:47:19-05:00Added an answer on July 26, 2022 at 4:47 am

      You guess. And you’ll be wrong. And that’s okay.

      Capacity is just a mechanism to help the team determine a Sprint Goal they can deliver; they’ll then inspect and adapt daily to meet that goal. But it’s okay to make a prediction (ie a Goal), get it wrong, then inspect and adapt.

      I’d suggest it’s more important to slice the work down into stuff that 1-2 people can do in 1-2 days, and make sure the team understands the work. A bunch of other stuff won’t go well in the first Sprint too.

      So – you’ll have a lot to unpack in the retrospective…

      • 1
      • Share
        Share
        • Share on Facebook
        • Share on Twitter
        • Share on LinkedIn
        • Share on WhatsApp

    Sidebar

    Ask A Question

    Stats

    • Questions 145
    • Answers 77
    • Best Answers 3
    • Users 0

    Top Members

    • Popular
    • Answers
    • Danny Vallee

      Is Kanban Agile?

      • 5 Answers
    • Anonymous

      What is one thing you wish you could know when ...

      • 2 Answers
    • Anonymous

      Testing generate a lot of bugs and the sprint never ...

      • 2 Answers
    • GuyM
      GuyM added an answer "The product backlog items are too big for one sprint"… March 5, 2023 at 12:45 am
    • GuyM
      GuyM added an answer I'd suggest two things. - the surface issue is seldom… March 5, 2023 at 12:36 am
    • Danny Vallee
      Danny Vallee added an answer Thanks GuyM! January 31, 2023 at 9:38 am

    Related Questions

    • How can we use agile practices to improve the diversity ...

      • 0 Answers
    • What are the most common mistakes that teams make when ...

      • 0 Answers
    • How to foster collaboration and trust in agile teams?

      • 0 Answers
    • How to deal with changing requirements in agile projects?

      • 0 Answers
    • How to Manage Scope Creep in an Agile Project

      • 0 Answers

    Trending Tags

    agile (6) book (4) metrics (4) po (5) scrum (10) scrum master (14) sprint (4) story (5) story points (4) team (9)

    Explore

    • Community Help
      • Kanban
      • Scrum
      • Scaled Scrum
      • Liberating Structures
      • Culture
      • Small Talk
      • Team Dynamics
      • Job Opportunities
      • Self-Promotions, Selling Services, Tool Promotions

    Footer

    About Us

    • Blog
    • Contact Us

    Help

    • Knowledge Base - FAQs

    Legal Stuff

    • Privacy Policy
    • Terms of Service

    © 2023 GaliléSolutions.com. All Rights Reserved
    Crafted with Love by Agile Lovers at GaliléSolutions.com.