Sign Up

Captcha Click on image to update the captcha.

Have an account? Sign In Now

Sign In

Captcha Click on image to update the captcha.

Forgot Password?

Don't have account, Sign Up Here

Forgot Password

Lost your password? Please enter your email address. You will receive a link and will create a new password via email.

Captcha Click on image to update the captcha.

Have an account? Sign In Now

Sorry, you do not have permission to ask a question, You must login to ask a question.

Captcha Click on image to update the captcha.

Forgot Password?

Need An Account, Sign Up Here

Sorry, you do not have permission to add post.

Captcha Click on image to update the captcha.

Forgot Password?

Need An Account, Sign Up Here

Please briefly explain why you feel this question should be reported.

Please briefly explain why you feel this answer should be reported.

Please briefly explain why you feel this user should be reported.

Sign InSign Up

Ask Agile

Ask Agile Logo Ask Agile Logo

Ask Agile Navigation

  • Home
  • Blog
  • Contact Us
Search
Ask A Question

Mobile menu

Close
Ask a Question
  • Community Help
    • Kanban
    • Scrum
    • Scaled Scrum
    • Liberating Structures
    • Culture
    • Small Talk
    • Team Dynamics
    • Job Opportunities
    • Self-Promotions, Selling Services, Tool Promotions
  • Home
  • Blog
  • Contact Us

Ask Agile Latest Questions

Anonymous
  • 1
Anonymous
Asked: November 14, 20222022-11-14T15:56:40-05:00 2022-11-14T15:56:40-05:00In: Scrum

How do you handle unplanned work throughout the sprint when there is so much unplanned work?

  • 1

Hi guys!

I have a team made up of devs, sre and architects. We have a product manager instead of a product owner but essentially they are the same thing I just think she has a little bit more responsibilities. The issue is my team does sprint work and support tickets like production support work that can come at any time, and a lot of times they come during the middle of the sprint. We call them unplanned work. These production tickets are also high priority items.

My question to you guys is how do you handle unplanned work throughout the sprint when there is so much unplanned work? Also I would like to note that this team do not have sprint goals and really struggle to provide them because so much of the work is unplanned and needs to be tracked.

unplanned work
  • 1 1 Answer
  • 35 Views
  • 0 Followers
  • 0
Share
  • Facebook

    You must login to add an answer.

    Captcha Click on image to update the captcha.

    Forgot Password?

    Need An Account, Sign Up Here

    1 Answer

    • Voted
    • Oldest
    • Recent
    1. GuyM
      GuyM
      2022-11-14T23:10:19-05:00Added an answer on November 14, 2022 at 11:10 pm

      The best thing to do is to plan for the unplanned work…

      That can take a few forms; one route is to leave a “buffer” for that unplanned work; in practice a buffer is *usually* a good idea anyway in a Scrum context. if you aim for the mean (average) velocity then half the time you will do more, and half the time you will do less.

      Having a buffer might also give you enough breathing space to be able to actually set a Sprint Goal, and start working towards the Product Goal step by step, doing Scrum “for real”

      In a Scrum sense you’d not usually ingest work that might imperil the Sprint Goal, and so a buffer allows you to pick up service tickets and still make progress.

      If you don’t want to do that, then maybe look at the Kanban Method; there you just pull work from the backlog. In the Kanban Method you have “classes of service”, one of which is Expidite; that’s pretty much where urgent work goes.

      However, there’s some deeper stuff to maybe unpack…

      – do you triage the production support tickets? Classifying them as “now”, “next Sprint” and “backlog” might be useful. Remember the Product Owner’s role is often about saying no to things, not saying yes to everything.

      – what generates the production support tickets? Can you do anything to eliminate or automate them?

      • 0
      • Share
        Share
        • Share on Facebook
        • Share on Twitter
        • Share on LinkedIn
        • Share on WhatsApp

    Sidebar

    Ask A Question

    Stats

    • Questions 145
    • Answers 77
    • Best Answers 3
    • Users 0

    Top Members

    • Popular
    • Answers
    • Danny Vallee

      Is Kanban Agile?

      • 5 Answers
    • Anonymous

      What is one thing you wish you could know when ...

      • 2 Answers
    • Anonymous

      Testing generate a lot of bugs and the sprint never ...

      • 2 Answers
    • GuyM
      GuyM added an answer "The product backlog items are too big for one sprint"… March 5, 2023 at 12:45 am
    • GuyM
      GuyM added an answer I'd suggest two things. - the surface issue is seldom… March 5, 2023 at 12:36 am
    • Danny Vallee
      Danny Vallee added an answer Thanks GuyM! January 31, 2023 at 9:38 am

    Related Questions

    • How can we use agile practices to improve the diversity ...

      • 0 Answers
    • What are the most common mistakes that teams make when ...

      • 0 Answers
    • How to foster collaboration and trust in agile teams?

      • 0 Answers
    • How to deal with changing requirements in agile projects?

      • 0 Answers
    • How to Manage Scope Creep in an Agile Project

      • 0 Answers

    Trending Tags

    agile (6) book (4) metrics (4) po (5) scrum (10) scrum master (14) sprint (4) story (5) story points (4) team (9)

    Explore

    • Community Help
      • Kanban
      • Scrum
      • Scaled Scrum
      • Liberating Structures
      • Culture
      • Small Talk
      • Team Dynamics
      • Job Opportunities
      • Self-Promotions, Selling Services, Tool Promotions

    Footer

    About Us

    • Blog
    • Contact Us

    Help

    • Knowledge Base - FAQs

    Legal Stuff

    • Privacy Policy
    • Terms of Service

    © 2023 GaliléSolutions.com. All Rights Reserved
    Crafted with Love by Agile Lovers at GaliléSolutions.com.